Q1.

Time, Work & Efficiency: $A$ can complete a railway track maintenance task in 12 days and $B$ in 18 days in 'Number System: Divisibility, Unit Digits, Fractions and Decimals'. If they work together, in how many days will the task be finished?

(A)

$7.2$ days ($\frac{12 \times 18}{12 + 18} = \frac{216}{30} = 7.2\text{ days}$) (Number System: Divisibility, Unit Digits, Fractions and Decimals)

(B)

6 days

(C)

8 days

(D)

9 days

Show answer & solution
Verified Answer & Solution Locked
Sign in to your free student account to reveal verified answers, instant hints, and detailed explanations.
Sign in to view
Q2.

Relative Speed & Crossing Platforms: A 240 m long train crosses a platform of length 360 m in 30 seconds in 'Number System: Divisibility, Unit Digits, Fractions and Decimals'. What is the speed of the train in km/h?

(A)

72 km/h ($\text{Speed} = \frac{240 + 360}{30} = 20\text{ m/s} = 20 \times \frac{18}{5} = 72\text{ km/h}$) (Number System: Divisibility, Unit Digits, Fractions and Decimals)

(B)

60 km/h

(C)

54 km/h

(D)

90 km/h

Show answer & solution
Verified Answer & Solution Locked
Sign in to your free student account to reveal verified answers, instant hints, and detailed explanations.
Sign in to view
Protected Questions

Unlock All 55 Questions in Fundamental Operations & Commercial Math

Log in or sign up free to access every question with complete solutions, create chapter practice tests, and track your performance.

Sign up free to access all 55 questions

Unlock every Fundamental Operations & Commercial Math question, generate papers, and practice at your own pace.